No |
STRUCTURE |
INVESTOR |
YEAR |
1. |
Glass melting furnace in SFS |
SFS Paraćin |
1982. |
2. | Pusher type furnace |
Sweden |
1991. |
3. |
Reconstruction of fume ducts above the HF201 furnace |
Oil Refinery Novi Sad |
1998. |
4. |
Furnace for vacuum oil destilation |
Oil Refinery Novi Sad |
1998. |
5. | Furnace BA 301 – 304 |
Oil Refinery Pančevo |
2000. |
6. | Furnace BA 101 |
Oil Refinery Pančevo |
2000. |
7. | Furnace 101 |
Oil Refinery Pančevo |
2001. |
8. | Disassembling of BA 201 furnace |
Oil Refinery Pančevo |
2002. |
9. | Disassembling of HF furnace |
Oil Refinery Novi Sad |
2002. |
10. | Overhaul of furnace BA-2201 A/B. |
Oil Refinery Pančevo |
2006. |
11. | High furnace overhaul. |
US Steel Smederevo |
2005. |
12. | Replacement of filling device in High furnace plant |
US Steel Smederevo |
2005. |
13. | Desing and manufacture of crane access road and pedestrian gallery around crane tracks BF 31- Blast furnace |
US Steel Smederevo |
2006. |
14. | KIA DOO – Nitrogen line erection on blast furnace |
US Steel Smederevo |
2007. |
15. | Replacement of furnace burner parts. |
TITAN „KOSJERIĆ Cement Plant” A.D. |
2007. |
16. | Production, delivery, and installation of stucture and fan for furnace wall cooling. |
TITAN „KOSJERIĆ Cement Plant” A.D. |
2007. |
17. | Production, delivery, and installation of clinker conveyor parts. |
TITAN „KOSJERIĆ Cement Plant” A.D |
2007. |
18. | Welding on furnace plant. |
TITAN „KOSJERIĆ Cement Plant” A.D. |
2007. |
19. | Production, delivery, and installation of equipment and parts for replacement of clinker bucket conveyor. |
TITAN „KOSJERIĆ Cement Plant” A.D. |
2007. |
20. | Preparatory works on VP-2. |
US Steel Smederevo |
2010. |
21. | Replacement of filling device VP2. |
US Steel Smederevo |
2010. |
METALLURGICAL EQUIPMENT
The Metallurgical Equipment Program has been implemented since 1950. For the requirement of the steel mill Zenica, GOŠA has undertaken the installation of a mixing plants, ground level charging machine, monorails, rocking type furnace. As many as 35000 tons of the equipment have been installed in various facilities of Smederevo Metallurgical Works, including anealing plant, dresser, rolling station, shears, converters, buggy conveyer equipment slitting shears, blast furnaces.
For only 18 months, GOŠA’s erection team has completed a blast furnace in Smederevo Metallurgical Works, volume 1386 cum, capacity 865.000 t. where 6000 tons of equipment and 7000 t of structure has been installed.
EXPERIENCE ON PROJECTS ABROAD
- Bangun – Central African Republic
OMIH sports hall
- Addis Abeba – Ethiopia
Exhibition hall
- Saudi Arabia – Dammam
Grain silo – 20 bins
- HE „BOALI II“ – CAR
Intake structures, pipelines and gates
- CHIRA PIURA – PERU
Pipelines, gates and linings
- DAR – ESSALM – TANZANIJA
portal crene for port 20/7/14/30,5
- TRIPOLI – BENGAZI –LIBYA
Dapartment stores 3 pcs
- VLAŠKI MEZIRIĆI – ČSSR
Colour TV factory
- AL IBTISSAM DAM
Algeria HNO
- MOSCOW – RUSSIA
Exhibition hall
- Seni Amrame
Algeria HN
- Zastakljena Al-fasada
Mongolija
- Fabrika zeolita
Talin
- Potisna peć
Švedska
Fabrika SIPOREX-a
Samara
- Fabrika lizina
Obuhov
- Fabrika margarina
Kazanj